Licensing factory construction in Vietnam need up to 166 days

The US-China trade war has greatly affected the world economy. However, Vietnam is benefiting from this upheaval. There are many enterprises relocating their operations from China to Vietnam. This means that the trend of building factories to operate will thrive. However, the problem is that the waiting time for construction permit procedures is too long. This is also the reason why many enterprises turn to factory renting solutions. And in the South in particular, workshop leasing services in Binh Duong, Dong Nai, Ho Chi Minh City and Long An have achieved much success. The following article will analyze the issues related to this situation.

The actual situation about the time of waiting for construction permit

Regarding granting construction permits, Ms. Tong Thi Hanh - Director General of Department of Legal Affairs acknowledged that the construction licensing criteria were evaluated by World Bank (WVB) as the highest-ranking criterion in Vietnam. However, the licensing time is still inadequate. Specifically, according to Ms. Hanh, the time to carry out construction licensing procedures in Vietnam is 166 days (according to the World Bank's assessment of 2017), which makes Vietnam become one of the countries with the longest implementation days. Meanwhile, the average of ASEAN countries is 66 days.

construction permit procedures

Ministry of Construction also "very concerned" about this issue. However, the procedure for construction permits involves many ministries and localities. These include: appraising the design of construction permits, appraising fire prevention and fighting, ... In order to improve this issue, it is necessary to have close coordination among relevant units. However, the fact that this improvement is not possible immediately. Therefore, enterprises must think of other alternatives. Renting ready-built factories through factory leasing service in Binh Duong, or Dong Nai, Ho Chi Minh City, Long An is the optimal choice in the South.

Alternatives for enterprises - finding factories for rent

While waiting for the permit to build up to 166 days, renting ready-built factories in industrial parks for rent Binh Duong, Long An solved this problem. The use of ready-built factories helps businesses optimize the waiting time for procedures. In only about 5 - 6 months, enterprises can go into official operation. The shortening of this investment time will help businesses quickly go into production. Thereby bringing about profits sooner and higher than the investment costs.

construction permit procedures

Not only that, renting a factory helps enterprises avoid the hassle of factory construction on their own. In addition to construction permits, enterprises also have to perform many other mandatory procedures. However, if they choose to rent factories, all problems will be solved. From there they will have more time for production and business activities.

Thus, limitations on the time for granting construction permit creates opportunities for the market of ready-built factories for rent. Never have the services of workshops for rent in Binh Duong, Dong Nai, Long An or Ho Chi Minh City have been "so successful". The article above is hoped to provide enterprises with the necessary knowledge.

 



Related

10/08/2018, News
Team Building 2018 for...
In September, Kizuna organized a team building for businesses operating in KIZUNA Serviced Factory, with the participation of 5 companies including...
02/28/2019, News
Chuyển đổi thuê bao...
Theo Bộ Thông Tin & Truyền Thông, các thuê bao di động 11 số đã được chuyển đổi sang 10 số. Các thuê bao di động 10...
04/09/2018, News
Certificate of Food Safety...
Pursuant to the Vietnam’s Food Safety Law No. 55/2010/QH12 entered into force on July 1st, 2011 and the relevant decrees and circulars,...
03/20/2019, News
Tổng kết tình hình...
Trong 6 tháng đầu năm 2017, tổng vốn FDI đầu tư vào Việt Nam là 19,22 tỷ USD, tăng 54,8% so với cùng kỳ năm 2016. Cả...
09/06/2018, News
Chia tay và hẹn gặp...
SEAPAC là DN sản xuất sản phẩm phục vụ ngành câu cá cho thị trường Mỹ. Đây là DN Hàn Quốc lần đầu tiên đầu...
09/02/2020, News
Semitec Electronics Vietnam...
On August 13th, 2018, The People’s Committee of Long An Province held a conference on the emulation movement of “Long An integration and...
09/15/2020, News
Nhà xưởng sản xuất...
Khi chọn lựa nhà xưởng sản xuất thì chi phí sẽ được xem là yếu tố "đủ". Vậy thì vị trí nhà xưởng sẽ...
02/28/2018, News
Printing business...
For foreign companies investing in Vietnam for the first time, they must be surprised by the investment procedures as well as the licenses required...